Expression of Interest;
M020 - Methanol Injection / Downhole Equalization;
Reference: EOI-DA-M020;
BIDS Category: 4900/4917/4971
Closing Date: 31 August 01
Use this reference for all correspondence: EOI-DA-M020
Issue date: 10 Aug 01
Sable Offshore Energy Incorporated (SOEI) has appointed Kvaerner SNC-Lavalin (KSLO) as their EPCM Contractor for the SABLE OFFSHORE ENERGY PROJECT Tier 2.
Companies interested in pre-qualifying to bid on project work should submit corporate resumes indicating relevant experience, capability and expertise with similar projects prior to the closing date indicated above. KSLO reserves the right to make the
final determination of which firms qualify to bid.
Contractor / Vendor shall note that the Owner may not have received project sanction at the time of Request for Proposal, however, it is the Owner's intention that project sanction and subsequent funding will be obtained for the scope of work outlined in
the Job Specification within the proposal validity period requested therein.
KSLO now seeks qualified contractors interested in providing the following:
Scope of Supply:
The design, fabrication and testing of one skid mounted mechanical equipment package unit for downhole well control and methanol injection, to be installed on an unmanned offshore gas platform located close to Sable Island off the coast of Nova Scotia.
Equipment to comply fully with all necessary Canadian Standards and Regulations.
Package will consist of double diaphragm injection pumps; carbon steel storage tank; pipework; valves; and calibration pots all assembled onto a single lift skid. Package will include high-pressure equipment to be designed and fabricated in accordance
with CSA B51, and requiring registration with the Nova Scotia Department of Labour. Equipment shall also be in accordance with API Spec 14D & API RP 14H.
Dual Compartment Tank - 1.0 mƯ compartments (2.0 mƯ total capacity), CS construction, 66/26 _C Temperature (Des/Op), 7/0 kPag Pressure (Des/Op)
Option to Increase Scope of Supply
Contractor / Vendor shall take into consideration the additional Sable Tier II platform requirements when preparing the submission for the Alma Development Project and the Owner's intent for the option to extend the current scope to future platforms where
applicable.
Schedule for Delivery
Bidding is planned for the mid to late 2001 with delivery required in the mid 2002. Contractors/vendors must advise typical lead time for this scope of work.
Experience
Potential bidders must demonstrate that they have previously supplied similar units for installation on an offshore platform located in an analogous environment.
Supplier Submissions
All enquiries and Expressions of interest should be directed to: KSLO Alma Development Project Suite 500 Centennial Building 1660 Hollis Street Halifax Nova Scotia Canada B3J 1V7 Attention: Procurement Manager Fax No.: (902) 490-8679
Email:almaproc@snc-lavalin.com
IN ADDITION: POTENTIAL CONTRACTORS TO SABLE OFFSHORE ENERGY INC., IF THEY HAVE NOT ALREADY DONE SO, MUST REGISTER THEIR COMPANIES BY CONTACTING BIDS AT: Phone; (902) 462-4824 1-800-397-0393 E-mail: bids@istar.ca